Situation 1: Not enough width
1 Cooperate with the trunking manufacturer to change the cross-sectional shape of the trunking if the pipeline can pass through or without reducing the cross-section.
2 Part of the pipeline can be changed to the form of pipe through.
3 Single-layer bridge is changed to multi-layer bridge to reduce the width of single layer.
4 The side wall fixing method can be used to increase the space.
Situation 2: Not enough height
5 Cooperate with the trunking manufacturer to change the cross-section shape of the trunking when the pipeline can pass through or without reducing the cross-section.
6 Under the premise of communicating with the design institute, the height of each floor can be reduced, but the minimum floor height is not less than 200mm.
7 Using an encrypted plane layout method can reduce the height of the crossbar and lower the elevation.